Getting electricity connected to a new home in Saudi Arabia is a step-by-step process that starts well before the first switch is flipped. Whether you are building a villa, splitting a property into independent units, or moving into a newly completed unit, the Saudi Electricity Company handles permanent connections through a clear digital workflow tied to your building permit. This guide from سعودي ليفنج walks you through each stage, from the paperwork you need to the fees, timelines, and compensation you are entitled to if things run late.
Before You Apply: Permits and Prerequisites
You cannot request a permanent electricity connection without a valid municipal building permit. Once the permit is issued, you apply for the connection through the Balady platform. Industrial projects follow a different track and may apply through Modon instead.
After the building permit is in hand, the next essential document is the Coordination Certificate. This certificate is where the technical details of your supply are defined, including:
- Whether service is available at your location.
- The location where meters will be installed.
- The required electrical load.
- The number of independent units.
- The breaker capacity.
- Cable specifications.
Treat the Coordination Certificate as the blueprint for your connection, because the fees and network work are calculated from the figures it contains.
Preparing the Site and Paying the Connection Fee
Before the connection can be completed, you need to prepare the meter location The connection fee itself is calculated from the approved breaker capacity and the amount of network work required.
The published connection-fee schedule gives you a sense of the range:
- SAR 828 for a 20-ampere breaker with 13.8 kVA capacity (typical for smaller residential supply).
- Up to SAR 138,000 for an 800-ampere breaker with 552 kVA capacity (larger and heavier loads).
Depending on the scope of your project, additional charges may apply, such as SAR 25,000 for preliminary study work, SAR 75,000 for planning, engineering, and supervision, and SAR 1,000 per power meter for low-voltage load division, including accessories and installation. Always confirm the exact figures for your case on the official Saudi Electricity channels, since they depend on your approved capacity and required works.
Adding a Meter to a New Independent Unit
If you have created a new independent unit, for example by dividing an existing property, you request a meter through Saudi Electricity's website or application by going to Electricity Service Management → Add Meter.
To add a meter you will need:
- A municipal building permit that shows the number of independent units.
- A field inspection carried out by the company.
You can submit the whole request digitally by uploading the required documents through the website or app, which saves you a trip to a service office.
How Long Connection Takes
Timelines depend on the type of network work involved:
- Low-voltage connections requiring network work: up to 20 working days after payment.
- Medium-voltage work: up to 60 working days.
Keep your proof of payment and application reference handy so you can track progress and hold the service to its published standard.
Compensation for Delays
If delivery is delayed beyond the committed timeframe, you may be entitled to compensation under the service-level conditions: SAR 400 plus SAR 20 for each additional working day or part of a day. Check the specific conditions attached to your service request, as eligibility is tied to the service-level terms.
Connection Fee vs. Consumption Tariff
It is important to separate two different things. The connection fee is a one-time charge for getting power to your property. The consumption tariff is what you pay for the electricity you actually use each month, and it is entirely separate.
a new electricity tariff is scheduled to take effect on 1 January 2027. This means 2027 tariff rates should not be treated as 2026 rates. For your current billing, always rely on the tariff published for the relevant year on the official Saudi Electricity channels.
Quick Checklist
- Secure a valid building permit.
- Apply through Balady (or Modon for industrial projects).
- Obtain the Coordination Certificate.
- Prepare the meter location to specification.
- Pay the connection fee based on approved breaker capacity.
- For a new unit, use Add Meter and arrange the field inspection.
- Track your request and note the delivery timeline.
Stay updated with the latest news, events, sports updates, business insights, real estate and lifestyle stories on Saudi Living — the leading online platform for residents, expats, and visitors in Saudi Arabia.
Follow Saudi Living for daily updates:
- Instagram - @saudiliving
- X - @saudiliving
- Facebook - @saudiliving
- YouTube - @saudiliving
Up Next

Paying Traffic Fines in Saudi: Najm vs Absher Guide
Learn the real way to pay Saudi traffic fines through Absher and Efaa, why Najm doesn't collect them, plus discounts and late-payment rules.
Nov 10,2026
Dependent Iqama Guide: Sponsoring Family in Saudi Arabia
A practical Saudi Living guide to sponsoring your spouse, children, and parents: eligibility, documents, fees, Muqeem, Absher, and renewals.
Nov 10,2026
Family Visit Visa for Saudi Arabia: Steps & Requirements
A practical guide to the Saudi family visit visa: eligibility, documents, step-by-step application through the unified visa platform, processing time and fees.
Nov 10,2026
Registering a Child's Birth in Saudi Arabia Guide
Step-by-step guide to registering a newborn's birth in Saudi Arabia via Absher — for citizens and residents, deadlines, fees, and documents you'll receive.
Nov 10,2026Related Stories
Don't Miss Similar Listings
Be the first to know when new stories on this topic are published.